References Underground Pipework

References Underground Pipework

Place for the big image

Commerzbank Arena

Deutschland

Bilfinger Berger betreibt...
Place for the small images

Pipeline 100 Puchkirchen – Haidach / Austria

Pipeline 100 Puchkirchen – Haidach / Austria Show Reference
Pipeline 100 Puchkirchen – Haidach

Client:   OÖ Ferngas Netz GmbH

 

Consortium Upper Austria: Bilfinger VAM / Kremsmüller

 

Scope of services :

▪Implementation of pipe work

▪34,3 km DN 800 PN 100

▪Wall thickness:   813 x 12,5 mm

▪Material:  L 485 MB

▪2 Pigging stations DN 800

▪2 Valve stations DN 800

 

Project duration: April 2013 – Oktober 2013 ▪

Pipeline 100 Puchkirchen – Haidach

Client:   OÖ Ferngas Netz GmbH

 

Consortium Upper Austria: Bilfinger VAM / Kremsmüller

 

Scope of services :

▪Implementation of pipe work

▪34,3 km DN 800 PN 100

▪Wall thickness:   813 x 12,5 mm

▪Material:  L 485 MB

▪2 Pigging stations DN 800

▪2 Valve stations DN 800

 

Project duration: April 2013 – Oktober 2013 ▪

Pipeline 100 Puchkirchen – Haidach

Client:   OÖ Ferngas Netz GmbH

 

Consortium Upper Austria: Bilfinger VAM / Kremsmüller

 

Scope of services :

▪Implementation of pipe work

▪34,3 km DN 800 PN 100

▪Wall thickness:   813 x 12,5 mm

▪Material:  L 485 MB

▪2 Pigging stations DN 800

▪2 Valve stations DN 800

 

Project duration: April 2013 – Oktober 2013 ▪

Gas Pipeline „ONTRAS“ / Germany

Gas Pipeline „ONTRAS“ / Germany Show Reference
Gas Pipeline „ONTRAS“ / Germany

Scope of services:
Editorial work and tube-building
- work gas pipeline
- 2 pig traps

Length: 14,2 km
Dimension: DN 600
Wall thickness: 11,2 mm and 14,2 mm
Material: L485 MB

Orderer: RWE Service GmbH
Consortium: Anton Meyer GmbH & Co KG / BIS VAM
Period of time for erection: September 2009 – 2010

Gas Pipeline „ONTRAS“ / Germany

Scope of services:
Editorial work and tube-building
- work gas pipeline
- 2 pig traps

Length: 14,2 km
Dimension: DN 600
Wall thickness: 11,2 mm and 14,2 mm
Material: L485 MB

Orderer: RWE Service GmbH
Consortium: Anton Meyer GmbH & Co KG / BIS VAM
Period of time for erection: September 2009 – 2010

Gas Pipeline „ONTRAS“ / Germany

Scope of services:
Editorial work and tube-building
- work gas pipeline
- 2 pig traps

Length: 14,2 km
Dimension: DN 600
Wall thickness: 11,2 mm and 14,2 mm
Material: L485 MB

Orderer: RWE Service GmbH
Consortium: Anton Meyer GmbH & Co KG / BIS VAM
Period of time for erection: September 2009 – 2010

Gas Pipeline „ONTRAS“ / Germany

Scope of services:
Editorial work and tube-building
- work gas pipeline
- 2 pig traps

Length: 14,2 km
Dimension: DN 600
Wall thickness: 11,2 mm and 14,2 mm
Material: L485 MB

Orderer: RWE Service GmbH
Consortium: Anton Meyer GmbH & Co KG / BIS VAM
Period of time for erection: September 2009 – 2010

Gas Pipeline „ONTRAS“ / Germany

Scope of services:
Editorial work and tube-building
- work gas pipeline
- 2 pig traps

Length: 14,2 km
Dimension: DN 600
Wall thickness: 11,2 mm and 14,2 mm
Material: L485 MB

Orderer: RWE Service GmbH
Consortium: Anton Meyer GmbH & Co KG / BIS VAM
Period of time for erection: September 2009 – 2010

Project „7 Fields - RAG“ / Austria

Project „7 Fields - RAG“ / Austria Show Reference
Project „7 Fields - RAG“ / Austria

Scope of services consortium Streicher-Bilfinger VAM:
Pipe fitting for the following construction sections:
- Section 1: Nussdorf – Auerbach 19 km DN 600 / 24“
- Section 2: Auerbach – Zagling 27 km DN 600 / 24“
- Section 3: Auerbach – Haiming 25 km DN 900 / 36“

Material: L 480 MB
Orderer: Max Streicher GmbH & Co KG
Period of time for realization: 2009 – 2010

Natural gas high pressure pipeline - „Pyhrn“ / Austria

Natural gas high pressure pipeline - „Pyhrn“ / Austria Show Reference
Natural gas high pressure pipeline - „Pyhrn“ Section B / Austria

Scope of services:
- Erection of the pipeline from Klaus to St. Pankraz, Upper Austria

Total length: 9 km, DN 400 / PN 70
Most difficult pipe laying on mountains, approx. 4 km pipe laying in a lake
2 culverts (Steyr, Teichl),
Material: STE 360.7
Length of pipeline in country: 5.333 m
Length of pipeline in the storage lake: 3.733 m
Orderer: Oberösterreichische Ferngas AG
Period of time of realization: Autumn 1997